Obtain environmental compliance |
B: 165. Produce Environmental Compliance Documentation for all applicable work on Coho Reintroduction |
|
01/31/2017 |
01/31/2017 |
Continue to develop operation plans and protocols |
C: 174. Hatchery Operations and Facility Plans |
|
12/01/2016 |
12/01/2016 |
Conduct and document maintenance and repair activities |
D: 61. Subcontract O&M for maintenance of facilities |
|
01/31/2017 |
|
Manage and administer project, February 1, 2016 through January 31, 2017 |
E: 119. Manage and Administer 2016-2017 Project for Mid Columbia Coho Restoration |
|
01/31/2017 |
|
Acclimated smolts released |
F: 176. Acclimation/Release: Wenatchee: Coulter Creek pond (BY 2014) |
|
06/30/2016 |
06/30/2016 |
Acclimated smolts released |
G: 176. Acclimation/Release: Wenatchee: Beaver Creek pond (BY 2014) |
|
06/30/2016 |
06/30/2016 |
Acclimated smolts released |
H: 176. Acclimation/Release: Wenatchee: Rohlfing's pond (BY 2014) |
|
06/30/2016 |
06/30/2016 |
Acclimated smolts released form Butcher Creek pond |
I: 176. Acclimation/Release: Wenatchee: Butcher Creek Pond (BY 2014) |
|
06/30/2016 |
06/30/2016 |
Acclimated smolts released |
J: 176. Acclimation/Release: Wenatchee: Leavenworth NFH (BY 2014) |
|
04/25/2016 |
04/25/2016 |
Acclimated smolts released |
K: 176. Acclimation/Release: Gold Creek Ponds (BY 2014) |
|
06/30/2016 |
06/30/2016 |
Acclimated smolts released |
L: 176. Acclimation/Release: Wolf Creek Pond (BY 2014) |
|
06/30/2016 |
06/30/2016 |
Acclimated smolts released |
M: 176. Acclimation/Release: Methow: Twisp Ponds (BY 2014) |
|
06/30/2016 |
06/30/2016 |
CWT or PBT mark fish BY2015 |
N: 158. Mark/Tag Animals - Subcontract CWT and/or PBT of approximately 1,500,000 BY15 coho pre-smolts |
|
01/31/2017 |
01/31/2017 |
Collection of 2016 Coho Broodstock: Wenatchee and Methow programs |
O: 66. Trap 2016 broodstock at Dryden, Tumwater, Wells, Methow FH, Winthrop NFH, and LNFH |
|
11/30/2016 |
11/30/2016 |
Spawn 2016 brood coho at Leavenworth NFH |
P: 176. Spawn 2016 brood coho at Leavenworth NFH |
|
11/25/2016 |
11/25/2016 |
Spawn 2016 coho broodstock at Winthrop NFH |
Q: 176. Spawn 2016 brood coho at Winthrop NFH |
|
11/26/2016 |
11/26/2016 |
Carcass distribution for BY2016 broodstock |
R: 44. Carcass dispersal of a portion of 2016 broodstock in the Wenatchee and Methow River programs |
|
01/15/2017 |
12/30/2016 |
Transport 2016 BY eyed coho eggs to rearing facilities |
S: 66. Transport 2016 brood eyed-eggs from incubation facilities to rearing facilities |
|
01/16/2017 |
01/16/2017 |
Coho redd counts and spawning composition for the 2016 return year |
T: 157. Conduct spawning ground surveys for the 2016 return year in the Wenatchee Basin |
|
01/31/2017 |
01/31/2017 |
2016 return year coho redd counts and spawning composition |
U: 157. Conduct spawning ground surveys for the 2016 return year in the Methow Basin |
|
01/31/2017 |
01/31/2017 |
Completed database |
V: 157. Collect biological data from 2016 coho brood at spawning |
|
01/31/2017 |
01/31/2017 |
CWT recovery data from the 2016 BY |
W: 157. Extract CWT from 2016 brood coho snouts collected at spawning and on spawning ground surveys |
|
01/31/2017 |
01/31/2017 |
PIT tag fish 2015 BY |
X: 158. Mark/Tag Animals - PIT-tag 58,000 BY15 coho pre-smolts |
|
01/15/2017 |
01/15/2017 |
Analyze data from 2016 BY |
Y: 162. Analyze and interpret M&E data from 2016 brood |
|
01/15/2017 |
01/15/2017 |
Enter data |
Z: 160. Enter data into and maintain local databases |
|
01/15/2017 |
01/15/2017 |
Collect data during 2016 emergence |
AA: 157. Collect/Generate Field and Lab Data to determine 2016 emergence timing, growth and distribution |
|
01/31/2017 |
01/31/2017 |
Completed Annual Report |
AB: 132. Submit Annual Report for the FY15 period (2/1/15 to 1/31/16) |
|
05/01/2016 |
09/30/2016 |
Tissue analysis by CRITFC for genetic monitoring |
AC: 157. Analyze genetic tissue samples for PBT analysis of parental groups |
|
01/31/2017 |
01/31/2017 |
Completed Annual Report |
AD: 132. Begin preparation for annual reporting of the CY16 period (1/1/16 through 12/31/16) |
|
01/31/2017 |
|
Produce genetic divergence journal article |
AE: 183. Journal article for CRITFC-Hagerman PBT work |
|
01/31/2017 |
|
Finish 3-step process and proceed to construction |
AF: 196. Finish 3-step process for MCCRP |
|
01/31/2017 |
|